Historical Combined Sewer Overflow Log

Historical Combined Sewer Overflow Log

Initiation Completion CSO Outfall Duration
Jan 3, 2025 6:49 am Jan 3, 2025 7:13 am Argyle St. 0.39 hrs
Jan 3, 2025 4:26 am Jan 3, 2025 6:40 am Argyle St. 2.23 hrs
Jan 3, 2025 4:25 am Jan 3, 2025 5:28 am Maitland St. 1.05 hrs
Jan 3, 2025 4:26 am Jan 3, 2025 5:28 am Maitland St. 1.03 hrs
Jan 2, 2025 9:46 am Jan 2, 2025 10:18 am Maitland St. 0.53 hrs
Jan 2, 2025 12:06 am Jan 2, 2025 9:46 am Maitland St. 9.65 hrs
Jan 2, 2025 12:22 am Jan 2, 2025 9:46 am Maitland St. 9.40 hrs
Jan 2, 2025 6:37 am Jan 2, 2025 8:22 am Argyle St. 1.75 hrs
Jan 2, 2025 12:27 am Jan 2, 2025 4:29 am Argyle St. 4.04 hrs
Jan 1, 2025 9:48 pm Jan 1, 2025 10:39 pm Argyle St. 0.84 hrs
Jan 1, 2025 9:33 pm Jan 1, 2025 10:31 pm Maitland St. 0.97 hrs
Jan 1, 2025 9:34 pm Jan 1, 2025 10:31 pm Maitland St. 0.96 hrs
Jan 1, 2025 3:47 am Jan 1, 2025 7:05 am Argyle St. 3.30 hrs
Dec 31, 2024 2:17 am Dec 31, 2024 6:34 am Argyle St. 4.27 hrs
Dec 30, 2024 12:44 pm Dec 30, 2024 1:07 pm Maitland St. 0.37 hrs
Dec 30, 2024 10:45 am Dec 30, 2024 12:31 pm Maitland St. 1.77 hrs
Dec 30, 2024 10:09 am Dec 30, 2024 10:46 am Argyle St. 0.63 hrs
Dec 30, 2024 10:13 am Dec 30, 2024 10:28 am Maitland St. 0.26 hrs
Dec 30, 2024 9:48 am Dec 30, 2024 10:05 am Maitland St. 0.29 hrs
Dec 30, 2024 4:23 am Dec 30, 2024 10:05 am Argyle St. 5.69 hrs
Dec 30, 2024 9:15 am Dec 30, 2024 9:35 am Maitland St. 0.33 hrs
Dec 30, 2024 7:34 am Dec 30, 2024 9:07 am Maitland St. 1.55 hrs
Dec 30, 2024 6:57 am Dec 30, 2024 7:33 am Maitland St. 0.60 hrs
Dec 30, 2024 4:26 am Dec 30, 2024 6:57 am Maitland St. 2.52 hrs