Historical Combined Sewer Overflow Log
Historical Combined Sewer Overflow Log
Initiation | Completion | CSO Outfall | Duration |
---|---|---|---|
Mar 7, 2025 3:07 pm | Mar 10, 2025 10:29 am | Argyle St. | 65.37 hrs |
Mar 10, 2025 7:50 am | Mar 10, 2025 8:18 am | Maitland St. | 0.46 hrs |
Mar 10, 2025 7:28 am | Mar 10, 2025 7:49 am | Maitland St. | 0.36 hrs |
Mar 10, 2025 6:44 am | Mar 10, 2025 7:20 am | Maitland St. | 0.60 hrs |
Mar 10, 2025 6:20 am | Mar 10, 2025 6:42 am | Maitland St. | 0.37 hrs |
Mar 10, 2025 5:44 am | Mar 10, 2025 6:04 am | Maitland St. | 0.33 hrs |
Mar 10, 2025 4:48 am | Mar 10, 2025 5:42 am | Maitland St. | 0.92 hrs |
Mar 10, 2025 3:10 am | Mar 10, 2025 4:32 am | Maitland St. | 1.38 hrs |
Mar 10, 2025 1:59 am | Mar 10, 2025 3:09 am | Maitland St. | 1.16 hrs |
Mar 10, 2025 12:08 am | Mar 10, 2025 1:58 am | Maitland St. | 1.84 hrs |
Mar 9, 2025 11:49 pm | Mar 10, 2025 12:07 am | Maitland St. | 0.30 hrs |
Mar 9, 2025 11:09 pm | Mar 9, 2025 11:49 pm | Maitland St. | 0.66 hrs |
Mar 9, 2025 4:55 pm | Mar 9, 2025 11:08 pm | Maitland St. | 6.22 hrs |
Mar 9, 2025 4:24 pm | Mar 9, 2025 4:54 pm | Maitland St. | 0.51 hrs |
Mar 9, 2025 1:40 pm | Mar 9, 2025 4:23 pm | Maitland St. | 2.72 hrs |
Mar 9, 2025 12:30 pm | Mar 9, 2025 1:39 pm | Maitland St. | 1.16 hrs |
Mar 9, 2025 11:38 am | Mar 9, 2025 12:28 pm | Maitland St. | 0.84 hrs |
Mar 9, 2025 9:45 am | Mar 9, 2025 12:28 pm | Tahsis | 2.71 hrs |
Mar 9, 2025 7:31 am | Mar 9, 2025 11:37 am | Maitland St. | 4.10 hrs |
Mar 7, 2025 8:57 pm | Mar 9, 2025 10:07 am | Bruce St. | 35.17 hrs |
Mar 9, 2025 9:28 am | Mar 9, 2025 9:45 am | Tahsis | 0.27 hrs |
Mar 7, 2025 4:46 pm | Mar 9, 2025 9:28 am | Tahsis | 38.70 hrs |
Mar 9, 2025 5:24 am | Mar 9, 2025 7:31 am | Maitland St. | 2.11 hrs |
Mar 8, 2025 1:51 pm | Mar 9, 2025 5:24 am | Maitland St. | 13.54 hrs |